Exciting progress on site with the tower crane well upright, providing a great vantage point of the foundations of the building for the images below.
- The level 1 ground floor slab has been poured, the Habitat Construction team able to push forward in lieu of recent wet weather.
- With the concrete base now established, works have commenced on the uprights and Form Deck for level 2 which will encompass the perimeter of the site.Â
Both of these tasks act as Critical Path for the project and will keep the teams focus over the coming weeks.
- The Level 2 slab will be split across 2 concrete pours, both scheduled to take place towards the end of this month.
From there, we should see the project go up a floor each month, with the final concrete pour to occur prior to Christmas shut down.
Below are some images of progress so far and the main milestones of interest.