Parkwoods Apartments - Construction Update Dec 21 & Jan 22
With the year fast coming to a close, the construction team at Parkwoods are finalising the Level 7 concrete slab pour and are on track to have all block work completed prior to the Christmas shutdown.
Internally, level 3 apartments are being sheeted, framing is underway on level 4 and window installation on level 5 is almost complete.
When the team arrives back on site in 2022, they will roll straight into erecting the trusses on the roof, while the internal fit outs will continue to kitchens, bench tops and vanities among the first items on the agenda.
By the end of January, internal finishes should be up to level 5 with trades routinely moving up levels as other works progress below.
Bearing another wet weather event, we’re tracking well for a Q2 2022 completion and will be in touch early next year to advise on timing to get moving with your mortgage brokers/banks for finance approvals.