August will see the team finish on Level 3 with concrete to be poured by the end of this week. This will be a major milestone for the project as the construction team will then move into the first apartment structures of the building.
Despite the recent COVID lock-downs in South-East Queensland, commercial construction sites have remained open and our team have implemented all of the relevant safety measures in relation to ensuring our site is ‘COVID Safe’.
Â
Below are some images of progress with the main milestones to point out being;
Â
- Scaffolding is now up to level 4 with concrete being poured this week for level 3.
- Once level 3 is poured, we should start seeing the more distinct shape of the first apartments coming from this podium level.
- Electrical lighting fit offs are being completed to level 1 & level 2 carparking areas.
- From here we expect to pour and jump a level roughly every 3 weeks, with top out expected prior to the Christmas shutdown.