Market Lane - Construction Update September 2021
Construction activity is progressing at a solid pace across the Market Lane site. With a great run of clear weather, the Habitat Construction team have continued to make significant progress with the final stretch well and truly in sight.
The last of the typical apartment slabs have now been poured on both towers, from here we will move into the penthouses and will have topped out both buildings by the end of September.
After that the roof structures and high level raking walls will then be finished by the end of October.
Below are some images of progress with the main milestones to point out being;
– East tower (Tower 1, The Collection), scaffold is now moving past level 12.
– West Tower (Tower 2, The Residences), scaffold is now moving past level 14.
– Internal fit out are now up to level 9 in the east tower and level 10 in the west tower.