Market Lane - Construction Update November 2021
The wet season has well and truly landed on the Sunshine Coast, thankfully our construction team have been hard at work internally, smashing through the fit outs on the lower levels. November has seen the roof trusses installed on the Eastern Tower 1, while the Western Tower 2 is due to have its roof erected by the end of December weather permitting.
Â
Internal fit outs are progressing well, with the bulk of the works on the lower levels nearing completion. Kitchen joinery installation is up to level 9, while the tiling to bathrooms and wet areas is up to level 8. Works on the external façade continue with the buildings distinct white tile finish now visible through the scaffolding on the northern elevation.

The SOHO Terraces are also underway, with deep excavation groundworks finalised and slab to be poured on the next sunny day! Pending further wet weather delays, Market Lane is on track for scheduled completion within the second quarter of 2022.