Activity on site has been progressing well and construction timeframe remain on track. You can see from
photos below, the distinct outlines of each tower are now beginning to emerge from the joined podium
on Level 4.
Progress with the main milestones to point out being;
– Ground floor apartments now have wall framing completed, have been roughed in with electrical and
plumbing plaster board walls will be going up this week. Window installation and painting are to follow.
– Podium Level 4 apartments are being framed out this week.
– East Tower (Tower 1, The Collection), scaffold is now up to Level 8 with concrete for Level 7 being
poured this week.
– West Tower (Tower 2, The Residences), is now up to Level 9 with concrete due to be poured next week.