Last week marked 12 months since the first sod was turned at Market Lane. Over the past year our dedicated construction team have been working rain, hail, and shine to construct the first residential apartment building in the new Maroochydore CBD.
We have seen some delays from supply chain issues which has slowed some trades, but all in all we are powering ahead and are still on target for completion.
Despite the recent COVID lock-downs in South-East Queensland, commercial construction sites have remained open and we of course have implemented all of the relevant safety measures in relation to ensuring our site is ‘COVID Safe’.
.

Below are some images of progress with the main milestones to point out being;
– East tower (Tower 1, The Collection), scaffold is now up to level 10 with concrete being poured this week and level 11 towards the end of the August.
– West Tower (Tower 2, The Residences), scaffold is now up to level 11, concrete being poured this week and level 12 towards the end of the August.
– Internal tiling is now up to level 5 in Tower 1 and level 7 in Tower 2, with works underway for the external tiling and fit outs to the lower levels.
– Kitchen and bathroom joinery fit outs are following closely behind the tiling.
– Works have commenced for the lift shafts and fit outs on both towers are due to be completed by the end of year.