Since construction commenced mid-2020, the Habitat Construction team have been steaming ahead.
This month’s construction milestones include having completed a massive concrete pour for the first half of our Level 4 podium slab. The concrete for the second half is planned for later this month.
The scaffolding that encompasses the exterior of the building is now setup to Level 5 and it’s from this point that we will see the distinct shape of the two separate towers start to come out of this podium level.
This will also show the first apartments starting to take shape by next month.
Service fit outs have begun on the lower completed levels, with electrical and lighting rough ins to the fire mains and sprinkler pipework installations firmly underway.